The street life in Malsch is in motion! Since May 19, 2025, the L 608 between Neumalsch and the Lidl supermarket has been subjected to a comprehensive renovation. The work aims to renew the lane ceiling on a distance of around 2.8 kilometers and also upgrade the damaged cycle path sections and the confluence area. On June 2, 2025, the second and last construction phase began, which is now about to be completed. According to rp.baden-wuerttemberg.de .
According to the latest information, the renovation work will be completed on Friday, June 13, 2025, which is significantly planned than originally planned. You have to say that this is a reason to be happy, because this is how traffic is released faster by the L 608 and the Sycow roundabout. The entire measure, which costs around 850,000 euros and is financed by the state, no longer requires excessive delays, since the traffic safety and diversions are dismantled next weekend.
Details for renovation
The renovation work includes the renewal of the upper asphalt layer, which can be found in a damage area of around 22,000 m². According to the information from bnn.de could be planned precisely, so that the existing traffic load could be planned so could be kept as possible.
For the first construction phase, the route from Neumalsch to the confluence of Daimlerstrasse was renovated in two weeks. This full closure was on May 19, as well as a detailed signage that was set up a week in advance. In the detour via L67, Daimlerstraße, Stephanstrasse, Benzstraße and Ottoecker-Straße, drivers were able to get to their goal again.
detours and restrictions
In the second construction phase, which begins at the confluence of Daimlerstrasse and extends to the Lidl, certain sections remained closed throughout to avoid disorders in the work. The construction work for the renewal of the lane ceiling was planned exactly in such a way that the Lidl supermarket can remain open on working days.
Here are the most important information about diversions:
- The detour from Malsch to Neumalsch leads via the L67 and L607.
- Small -spacious diversions within Malsch enable access to shops.
- Turning from Daimlerstraße to the L608 to the north to the B3 is possible.
- to protect cycling, secure crossings were installed, including a traffic light on the B3.
The renovation of the L 608 not only focuses on road quality, but also affects the development of commercial transport, which will secure mobility for both residents and business people in the long term. A well-developed road network structure is essential for everyone involved, also as you can see on berlin.de that also set economic impulses.
The conclusion of these construction measures is personally expected, because the time of the diversions is coming to an end and the residents can soon look forward to more fluid traffic conditions.