Construction sites in Ludwigsburg: These streets are now blocked!

Construction sites in Ludwigsburg: These streets are now blocked!

Ludwigsburg, Deutschland - in Ludwigsburg, on Monday, June 14th, it will be properly down to business, because numerous construction sites and closures ensure traffic disruptions. Drivers and pedestrians should adapt to some diversions and restrictions. Abelstraße and Alter Oßweiler WEG are particularly affected, where full closures can be expected by the end of December and October in order to carry out the necessary work for district heating and the development of the Fuchshof. According to Ludwigsburg24 , the Beethovenstraße between house numbers 64 and 70 will probably only be accessible on half-sided, while the sidewalks remain.

But that's not all: In Birklenstrasse, drivers have to prepare for a full closure by July 16, since a sewer and house connection is laid here. It will also be tight in Fuchshofstrasse, because the footpaths are closed until October. Hohenzollernstraße, on the other hand, will only be passable to a limited extent by the end of June. Here private demolition work runs that bring temporary diversion.

full closures and restrictions

The further restrictions include full closure on kindergarten path until July 20 and the Lange Strasse, which is closed to car traffic until July 27th. In Liebenzeller Straße, drivers have to expect traffic impairments by the end of July, as the fiber optic expansion is progressing. The Upper Berg will also be closed to traffic until the end of November, since a supply pipeline for natural gas is being built here.

  • Current construction sites:
  • Abelstrasse: full closure by the end of December
  • Alter Oßweiler Weg: full closure until October
  • Beethovenstraße: half -side closure until July 16
  • Birklenstraße: full closure until July 16
  • Kindergartenweg: full closure by July 20
  • Lange Straße: full closure until July 27th
  • Liebenzeller Straße: full closure by the end of July
  • Oberer Berg: full closure by the end of November

On the motorways around Ludwigsburg, the challenges last, as current reports from stau.info . There are several incidents on the A81 between Stuttgart and Heilbronn, such as a defective vehicle on the hard shoulder and dangers from objects in the Engelberg tunnel. In addition, drivers in the Engelberg tunnel and on the A8 have to expect sporadic traffic disruptions. The accident site has now been cleared on the B10 at Mühlacker, and the A831 also reports all -clear after an oncoming vehicle.

outlook on road construction

As far as the general situation in road construction is concerned, it can be seen that the expansion of the highways is still a central concern, as an analysis of Statista In 2023, the Federal Running Straße network comprised around 13,200 kilometers. Despite an increase in sales in the previous years, the sector had to record a decline last year. While road construction is the most important sector in civil engineering, the investments for expansion are planned to almost 9.8 billion euros by 2028. Nevertheless, the expansion of the highways has stagnated since 1995, which gives additional pressure to maintain and maintain the street infrastructure.

With this information, the citizens of Ludwigsburg are well prepared in order to cope with the upcoming traffic impairments and road construction projects in the coming weeks. Stay informed and, if necessary, take into account alternative routes!